Deadline for KIA road will not be met

SLOVAKIA will not complete a motorway linking Bratislava and Žilina by November 2006, as it undertook to do according to an investment contract with the carmaker Kia Motors, Transportation Minister Pavol Prokopovič said on September 12.

Prokopovič told reporters that the Sverepec-Považská Bystrica-Vrtižer stretch (Trenčín region) would not be completed until the summer of 2007, the TASR news wire reported.

"The delay is because of a delay in planning permission, which was belatedly issued by the Považská Bystrica town council in May of this year, one year later than originally planned. Although we managed to cut preparatory work from a year to eight months, this time loss cannot be made up," said Prokopovič.

Construction of this stretch is expected to begin in January 2006. Other stretches should be completed on time.

Top stories

Ombudswoman: I need to point out human rights violations Photo

Mária Patakyová explains her support for the recent Rainbow Pride in Bratislava, following the criticism of a junior coalition partner.

Ombudswoman Mária Patakyová

Jaguar plant in Nitra will be bigger

The carmaker plans to add a new facility and employ more people.

Jaguar Land Rover plant near Nitra is under construction

Government members met at a distance

The session had only one point on its programme: the mandate for the prime minister to meet with the French president.

It’s not easy to be friends with Fico

Will Andrej Danko take the government down with him?

Andrej Danko