Spectator on facebook

Spectator on facebook

Court to decide on permit to complete Mochovce nuclear power plant

The Regional Court in Bratislava is due to rule today (Friday, May 11) in the case of the contested construction permit for completion of the third and fourth units of the Mochovce Nuclear Power Plant, the SITA newswire reported, citing Greenpeace Slovakia spokesperson Lucia Szabová.

The Regional Court in Bratislava is due to rule today (Friday, May 11) in the case of the contested construction permit for completion of the third and fourth units of the Mochovce Nuclear Power Plant, the SITA newswire reported, citing Greenpeace Slovakia spokesperson Lucia Szabová.

Greenpeace filed a motion against the Nuclear Regulatory Authority three years ago regarding completion of the plant. "The essence of the objection is that the Nuclear Regulatory Authority did not issue the construction permit in 2008 in a lawful manner," the spokesperson stated.

Greenpeace Slovakia argues that the issue of the permit should have been preceded by expert and public assessment of environmental impacts in an EIA process, which, according to Szabová, is an essential basis for each building permit procedure with a significant environmental impact.

"The Aarhus Convention Compliance Committee decided on this case in 2010 and assessed the compliance of the building permit issuing process with the Aarhus Convention, to which Slovakia is a signatory," she said, adding that the committee noted that Slovakia had violated the convention in issuing the permit to build the third and fourth unit of Mochovce, as it did not allow the public to engage early and effectively in the proceedings, through the EIA process. According to Greenpeace Slovakia and its lawyer Eva Kovačechová, the original building permit was issued in 1986, when the EIA process was not yet part of the Slovak legal system.

"In 2008, when construction of the nuclear power plant was renewed, the EIA process had already been included in the standard permitting process," she said. In her words, the Aarhus Committee did not take into account the argument of the Nuclear Regulatory Authority, according to which it did not need to conduct an EIA process to amend the building permit because it only allowed changes to an existing permit and did not issue a new one. However, the Aarhus Committee stated that such a significant change of the building permit should have been preceded by an EIA process. According to Szabova, the changed building permit contained many design changes to the NPP, for example regarding security and new technologies. "The changes were so significant in our view that we demand an EIA be carried out," she said, as quoted by SITA.

Source: SITA

Compiled by Zuzana Vilikovská from press reports
The Slovak Spectator cannot vouch for the accuracy of the information presented in its Flash News postings.

Top stories

Infertility in men is increasing with those in their 40s better off then those in their 20s

Treatment of infertility can cost tens, or even several thousand euros. Only part of the cost is covered by health insurance companies.

To be fertile, a man has to have 15 million sperms per milligram of ejaculate, of which 4 million must be healthy.

Czechoslovakia could have been Switzerland

In Hodonín and Holíč, Czechoslovakia still exists.

In Holíč, the border is basically non-existent.

Foreigners again used Slovak guns to kill

Although the international operation began in March, no investigator contacted a Slovak dealer.

AFG was selling large numbers of expansion weapons, which were in fact old deactivated military weapons.

Foreigners: Top 10 events in Bratislava Video

Tips for the top 10 events in the capital between December 15 and December 24, plus regular services in different languages, training, temporary exhibitions and highlights of the year.

Music exchange