6. July 2016 at 11:15

Clark: Complexity of the project has changed

John Clark managing the final works on the third and fourth units of the nuclear power plant Mochovce spoke about the project and more.

John Clark (r) reporting about completion works at Mochovce on June 24. John Clark (r) reporting about completion works at Mochovce on June 24. (source: Jana Liptáková)
Font size: A - | A +

While the current world is obsessed with renewable energy John Clark believes in a mix of energy resources and that nuclear energy, as a viable and reliable source of energy, has its place in it.

After having worked for almost five years for the Italian energy concern Enel in Russia, Clark was recently appointed to manage final works on the third and fourth units of the nuclear power plant Mochovce of Slovenské Elektrárne (SE). The Slovak Spectator spoke with Clark about completion of the second two units of Mochovce and more.

SkryťTurn off ads
SkryťTurn off ads
Article continues after video advertisement
SkryťTurn off ads
Article continues after video advertisement

The Slovak Spectator (TSS): You have become the new project director of completion of the third and fourth units of the nuclear power plant in Mochovce some weeks ago. In what condition was the project when you took over?

John Clark (JC): I only came here three months ago, but I have had the opportunity to visit the site several times even since 2007 [Ed. note: the completion of Mochovce third and fourth units started in 2008]. So between then and now at least I have been able to see the evolution of the activities on the site. On unit 3 we are now very advanced, although sometimes it is hard to understand when you are actually on the site because it seems that there is still a lot of work going, but most of them are minor finishing works. So at the end of May we had 92.5 percent of completion of unit 3, which means construction is basically completed. Major things that we have to complete are the installation of remaining cables and connection of the cables, and all the testing and commissioning we have to do before we can do cold and hot hydrostatic tests, fuel loading and then really start with the reactor.

SkryťTurn off ads
Third block of NUKE Mochovce closer to completion
Read also:
Third block of NUKE Mochovce closer to completion

TSS: When you took over this project three months ago, were you satisfied with how it was managed in the past?

JC: Satisfied is big word. I think we are never satisfied and that we are always looking for things to improve, to optimise the team and to optimise whether we manage things. So it has never really been a project where we stood still and were satisfied, that would say that what we are doing is enough because it is never enough. I think that over the last one year or one-and-half-years the project has made very good progress.

TSS: Do you thing that your predecessors managed this project properly?

JC: I think that the people who’ve been here were very committed and done quite a good job. My coming to this position was not really a reflection on the people who’ve been here before. It was more in the direction of further strengthening of the project team, so to have an additional experienced person here.

SkryťTurn off ads

And also for the future because you know we have a new shareholder entering, EPH. My role is not only for the management of the project, it is also for the management of the relationship with EPH.

TSS: So what exactly is your role here?

JC: Very clear task – to complete Mochovce to the right level of quality, reliability and safety and successfully transfer it to the operations.

TSS: Nicola Cotugno, general director of SE, showed on the press conference in Mochovce on June 24 a graph depicting how electricity prices dropped since the time when the decision to complete Mochovce was made. Is it worth it to complete Mochovce?

JC: Projects like this are not measured by the power price you see one day, one month or one year. The investment in major plants like this, whether it is nuclear or non-nuclear, is a substantial investment that takes a substantial time to implement. Major investments need a long-term market view. Of course, it is true that the market is changing, the world we have today is completely different compared to the world we had five years ago, but we still believe that Mochovce has its place on the market for the future. We believe that it is correct to finish the project. You do not make a €4.6 billion investment to abandon it a few hundred million euros from the end. It would be the wrong thing for the shareholders, the country as well as the market. The company, the market, the shareholders have an expectation that we will finish this project.

SkryťTurn off ads

Up to now we were only investing, we haven’t had any return, every euro generated by SE has been put into investment; none of them is going to the shareholders as dividends. So it is clear that it would be a wrong decision not to continue.

TSS: Is there a chance that Mochovce will be profitable?

JC: I think so. I think nobody builds a plant with the expectation that you will not be profitable. So, we have to work to complete the plant correctly and we have to work during the operational affairs to insure that the plant is profitable. In any business you don’t just except the conditions which exist, you have to work to make the conditions correct in order to have a profitable business.

TSS: What has to happen for Mochovce to become profitable?

The rest of this article is premium content at Spectator.sk
Subscribe now for full access

Subscription provides you with:

  • Immediate access to all locked articles (premium content) on Spectator.sk

  • Special weekly news summary + an audio recording with a weekly news summary to listen to at your convenience (received on a weekly basis directly to your e-mail)

  • PDF version of the latest issue of our newspaper, The Slovak Spectator, emailed directly to you

  • Access to all premium content on Sme.sk and Korzar.sk

SkryťClose ad